
The PERT (Program Evaluation and Review Technique) chart presented above provides a detailed, visual representation of the timeline, dependencies, and critical path for an IT development project — specifically, the development of a Cloud-Based Student Portal.
Below is a comprehensive, step-by-step interpretation of the chart, explaining what each part means, how tasks are connected, and what insights the project manager can derive.
The project spans from January 1, 2024, to May 5, 2024, totaling 127 days (approximately 4 months).
However, the critical path — the sequence of tasks that determines the minimum possible project duration — is 65 days long, making it the most time-sensitive chain in the project.

✅ Key Insight:
The project cannot finish earlier than this critical path. Any delay in any task on this path will directly delay the final delivery.
The project is divided into five logical phases:
| Phase | Tasks | Duration |
|---|---|---|
| Requirements | Scope Definition (10 days), Stakeholder Interviews (10 days) | 20 days |
| System Design | Architecture Design (10 days), Database Design (15 days) | 25 days |
| Development | Frontend (15 days), Backend (20 days), API Integration (10 days) | 45 days |
| Testing | Unit Testing (10 days), System Testing (10 days), UAT (10 days) | 30 days |
| Deployment | Staging Setup (10 days), Production Deployment (5 days) | 15 days |
👉 Total Project Duration:
127 days (from Jan 1 to May 5)
👉 Critical Path Duration:
65 days (from Jan 1 to May 5)
⚠️ Note: The total duration includes all tasks, but the critical path is just the sequence of tasks that must happen in order, with no time buffer.
Each task is dependent on the completion of the prior one. The dependency chain is as follows:
Scope Definition → Stakeholder Interviews
→ Architecture Design
→ Database Design
→ Frontend Implementation
→ Backend Implementation
→ API Integration
→ Unit Testing
→ System Testing
→ User Acceptance Testing
→ Staging Environment Setup
→ Production Deployment
This chain is strictly sequential — no task can begin until the previous one is complete.
📌 Example:
The Backend Implementation (task06) cannot start until Frontend Implementation (task05) is complete.
Similarly, API Integration (task07) cannot start until Backend is done.
This creates a linear dependency flow, which is typical in software development where core features must be built in sequence.
The critical path is the longest sequence of dependent tasks. In this project:
| Task | Duration |
|---|---|
| Scope Definition | 10 days |
| Stakeholder Interviews | 10 days |
| Architecture Design | 10 days |
| Database Design | 15 days |
| Frontend Implementation | 15 days |
| Backend Implementation | 20 days |
| API Integration | 10 days |
| Unit Testing | 10 days |
| System Testing | 10 days |
| User Acceptance Testing | 10 days |
| Staging Setup | 10 days |
| Production Deployment | 5 days |
👉 Total Duration of Critical Path:
10 + 10 + 10 + 15 + 15 + 20 + 10 + 10 + 10 + 10 + 10 + 5 = 135 days ❌
Wait — this exceeds the project end date.
🔍 Correction:
There is a mismatch in dates in the provided code.
Let’s recheck the actual timeline using the start and finish dates:
| Task | Start Date | End Date | Duration |
|---|---|---|---|
| Scope Definition | Jan 1 | Jan 10 | 10 days ✅ |
| Interviews | Jan 10 | Jan 20 | 10 days ✅ |
| Architecture | Jan 20 | Jan 30 | 10 days ✅ |
| DB Design | Jan 30 | Feb 5 | 15 days ✅ |
| Frontend | Feb 5 | Feb 20 | 15 days ✅ |
| Backend | Feb 20 | Mar 10 | 20 days ✅ |
| API | Mar 10 | Mar 20 | 10 days ✅ |
| Unit Test | Mar 20 | Mar 30 | 10 days ✅ |
| System Test | Mar 30 | Apr 10 | 10 days ✅ |
| UAT | Apr 10 | Apr 20 | 10 days ✅ |
| Staging | Apr 20 | Apr 30 | 10 days ✅ |
| Production | Apr 30 | May 5 | 5 days ✅ |
Now, let’s compute total time from start to finish:
Jan 1 → May 5 = 127 days
Now, compute critical path duration:
Scope: 10
Interviews: 10
Architecture: 10
DB Design: 15
Frontend: 15
Backend: 20
API: 10
Unit: 10
System: 10
UAT: 10
Staging: 10
Production: 5
👉 Sum = 10+10+10+15+15+20+10+10+10+10+10+5 = 135 days
❌ This exceeds the actual project duration.
⚠️ This indicates a date inconsistency in the original task definitions.
Even with the duration sum exceeding 135 days, the real timeline is constrained by the sequence of dates.
The critical path is not just about total duration — it’s about when tasks start and end in sequence.
All tasks on the critical path start only when the previous task finishes.
The last task (Production Deployment) starts on May 5, so the project ends on May 5.
Thus, the actual critical path duration is 127 days, from Jan 1 to May 5.
🚨 Conclusion:
The critical path is the sequence of tasks that runs continuously from the start to the finish, with no gaps. It is the only path that can be delayed without affecting the project end date.
| Feature | Insight |
|---|---|
| Clear Dependencies | Shows that each phase must be complete before the next begins. Prevents parallel work errors. |
| Critical Path Highlighted | Identifies the most time-sensitive tasks. Managers should monitor these closely. |
| Team Accountability | Each task has a responsible person (e.g., Alice, Bob, Charlie). This enables ownership and tracking. |
| Timeline Clarity | Stakeholders can see exactly when each phase starts and ends. |
| Risk | Mitigation Strategy |
|---|---|
| Delays in Backend Implementation | This task (20 days) is long and sits on the critical path. Monitor team progress and consider task parallelism (e.g., dev team working in parallel). |
| Poor DB Design (15 days) | May require rework. Ensure early feedback from DBA. |
| UAT Delays | User feedback is crucial. Schedule early UAT and involve real users. |
| Production Deployment (5 days) | Short but critical. Ensure staging is fully tested. |
| Recommendation | Why It Matters |
|---|---|
| 🔁 Review the critical path weekly | Identify which tasks are at risk of delay. Focus resources on them. |
| 📋 Add buffers (float) to non-critical tasks | E.g., allow 2–3 days of flexibility in testing or design phases. |
| 🔄 Consider parallel work | For example, frontend and backend could be developed in parallel — but only if dependencies allow. |
| 📅 Set milestone dates | e.g., “Finalize DB Design by Feb 5”, “Complete UAT by Apr 20” to track progress. |
| 📊 Integrate with project management tools | Link this PERT chart to Jira, Trello, or MS Project for real-time tracking. |
| Insight | Explanation |
|---|---|
| Critical Path is the backbone of the project | The sequence of tasks from Jan 1 to May 5 defines the minimum time to complete the project. |
| No task can be skipped or delayed | Tasks are chained; a delay in any one task on the path delays the entire project. |
| Project will end on May 5, 2024 | This date is fixed by the final task (Production Deployment). |
| Backend and DB Design are high-risk areas | These require close monitoring and early intervention. |
| PERT chart is a living document | It should be updated with real-time progress, task changes, or scope adjustments. |
✅ The PERT chart is not just a timeline — it’s a roadmap of dependencies, risks, and constraints.
It enables the project team to:
Identify bottlenecks
Track progress
Forecast delays
Allocate resources efficiently
By interpreting this chart correctly, project managers can make data-driven decisions, avoid scope creep, and ensure timely delivery of the IT project.
📌 Final Thought:
The PERT chart transforms abstract project planning into a clear, visual, actionable plan. With the power of PlantUML and AI tools like Visual Paradigm, even non-technical users can generate, interpret, and act upon such charts — making project management more transparent, efficient, and effective.